Bahrain Al Dur Phase II Project Block10 completes the pipe blowing

2021-11-29 11:42:04

At 16:56 of November 25, the pipe blowing for Bahrain Al Dur Phase II Project Block10 unit was accepted successfully, that marking the smooth realization of another importantmilestone of the project.

Block10 adopted 11/12 HRSG alternate blowing cooling method. According to the standard of stabilized pressure shooting, the shooting duration was more than 15 minutes and two consecutive shooting met the standard, which was highly praised by the project owner. In order to ensure the smooth implementation of Block10 pipe blowing, the project made advanced planning and scientific organization, promoted various works of Block10 pipe blowing steadily. During pipe blowing, all departments cooperated closely and implemented various safety and technical requirements strictly, providing a solid guarantee for the successful completion of Block10 pipe blowing with high quality.

The successful completion of Block10 pipe blowing marks the formal opening of the combination cycle commission of the project.



黄页网址大全免费李崇端60集视频午夜视频中文字幕亚洲男人的天堂网络浮乱转校生第2部完整txt5g影视链接链接链接